Before a renovation starts, find out the condition of the existing wiring and switchboard, decide where every socket, switch, light, heat pump and fan will go, and check the board has the space and capacity for the new circuits. Those three things decide most of the electrical budget, and they are far cheaper to sort out while the walls and ceilings are open. This guide covers what to check, what to plan, and how to avoid paying twice.
1. Find out what you are working with
Level (BRANZ) advises establishing "the age and condition of the wiring and distribution board before starting work on an existing building." In older villas, bungalows and mid-century homes, that check can change the plan:
- Fuses and rubber-sheathed wiring. Level notes that some houses have "the fuses on the main board, and wiring consisting of rubber-sheathed wiring in metal conduit", and that "the wiring is likely to be unsafe and should be replaced."
- Early plastic-sheathed (TPS) cable. Level says "early installations of TPS (tough plastic sheathed) cable may also be in poor condition".
- Three-plate lighting wiring. Level warns that in this configuration, "even when the light is not switched on, the phase wire at the light fitting remains live."
Ask your electrician to inspect and test before you finalise the budget. If the results point to replacing old circuits, it is much cheaper to do it during the renovation than after. Our guide on when to rewire a house explains the options, from partial to full rewiring.
2. Check switchboard space and capacity
Renovations add circuits: a new kitchen may add an oven, an induction cooktop, a dishwasher and a rangehood; a new bathroom adds a fan and a heated towel rail; an extension adds lighting and power. Level states that "all new lighting and power outlet circuits installed in electrical installations must be protected by one or more RCDs" (permanently connected appliances excluded). If your board has no RCDs or no spare space, plan an upgrade as part of the job. See signs you need a switchboard upgrade.
Also think beyond this renovation. If a heat pump, EV charger or spa pool is on the list for the next few years, size the board for it now.
3. Plan heating, cooling and ventilation at the same time
A renovation is the natural time to add or upgrade heating, because pipe routes, condensate drains and cabling can be hidden inside walls and ceilings before they are lined.
- High-wall heat pumps. Decide the wall position, outdoor unit location and pipe route now. Our guide to where to install a heat pump covers placement, and the heat pump size calculator gives a preliminary size for each room.
- Ducted systems. If the ceiling is coming down anyway, a ducted heat pump may become practical where it would otherwise be disruptive.
- Extraction fans. Kitchens and bathrooms need extraction to remove moisture at source. Plan the fan positions and duct runs to the outside with the lighting layout. See home ventilation.
- The electrical side. Each heat pump needs a circuit to the manufacturer's specification, and its load should be included when checking your maximum demand.
Because Plexus does electrical, heating, cooling and ventilation, we can plan all of these in one layout instead of three trades working around each other.
4. Lighting and downlights
Renovations often add downlights. Level (BRANZ) lists three problems with older recessed downlights: insulation must be kept clear of them to prevent overheating, holes in the ceiling let heat escape and undermine insulation, and moist air escaping into the roof space can cause condensation and mould. BRANZ recommends replacing older downlights with surface-mounted lights or IC or IC-F rated downlights, which can be covered by insulation, and replacing the whole fitting, not just the bulb.
Plan switching too. Level recommends switches at entry and exit points, two-way switching for rooms with more than one entrance and for stairs, and separate control for task and accent lighting. Our home lighting design guide covers this in more detail.
5. Sockets, data and the details people forget
Walk through each room with your furniture layout in mind and mark:
- sockets either side of beds, at desks and along every kitchen bench run;
- sockets and data at the TV position and in the home office;
- outdoor weatherproof sockets and exterior lighting;
- wall space for the heat pump controller and alarm keypad;
- any cabling for cameras or an intercom.
Level (BRANZ) also suggests considering "additional conduits or draw wires to roof, wall and underfloor spaces" during construction or renovation, so future changes do not mean opening walls again.
6. Smoke alarms
Level (BRANZ) notes that smoke alarms are mandatory in new residential work, including alterations that need building consent, and that "installing or replacing a hard-wired alarm must be done by a licensed electrician." If you are consenting the renovation, ask your designer what the consent requires.
7. Living in the house during the work
If you are staying in the house, agree with your electrician how power will be kept on to the parts you are living in, how long any shutdowns will last, and where temporary power for the builders will come from. A clear plan avoids surprises such as a fridge off for a day.
8. Sign-off and certificates
Your electrician must issue a certificate of compliance for general and high-risk prescribed electrical work, and an electrical safety certificate once the work is complete and safe to use, under the Electricity (Safety) Regulations 2010. If the renovation has a building consent, section 92 of the Building Act 2004 requires the owner to include any energy work certificate relating to the energy work with the application for a code compliance certificate. Keep copies with your house records.
Renovation electrical checklist
| Stage | Electrical task |
|---|---|
| Before design is final | Inspect and test existing wiring and switchboard; decide heating, cooling and ventilation |
| Design | Lighting, socket and data layout; switchboard upgrade if needed; smoke alarm positions |
| Demolition | Make safe and disconnect affected circuits; temporary power |
| Rough-in | New cables, heat pump cabling and pipe routes, fan ducts, data and security cabling |
| Fit-off | Switches, sockets, lights, fans, appliances, heat pump connection |
| Completion | Testing, certificate of compliance and electrical safety certificate |
Next steps
Talk to us before your renovation design is final. Read about our renovation electrical service, and if old wiring is a concern, our rewiring service. When you have plans or a scope, request a quote.
Sources
This guide is general information for New Zealand homes, not advice for your specific property. For a recommendation that accounts for your house, ask us.